Appendix A: Startup Checklist
Observing Conditions
Dome
- Open dome main shutter then the drop-out shutter.
- Open and latch the dome door.
- Turn off air conditioner.
Telescope & Instrument
- Open MIS dark hatch
- Leave the mirror covers closed until ready to collect data
- Fill instrument dewar with liquid nitrogen if required.
- Move the LN2 storage dewar, ladder, etc. away from
the telescope to the northeast corner of the platform.
- Lower the moving platform all the way down.
Computers
- Login to mcgraw as user obs13m, password posted
on dry the erase board.
Telescope Control System
- Turn the key and then press the TELESCOPE CONTROL START button.
- Turn the sidereal drive rotary switch to 60 Hz.
- Turn TCS MONITOR on the TELESCOPE CONSOLE on and adjust
brightness and contrast as desired.
- Turn the TCS MONITOR in observing room on.
- Start the xtcs window on the Linux station "mcgraw" if not
already started.
MIS and Guider
Turn on the following units:
- Turn on the GUIDER PC, if not already on. It will automatically start
the TVGUIDER program.
- Turn on the CAMERA POWER SUPPLY.
- Turn on the GUIDE MONITOR.
Updated: 2006-04-04